PROJECT STATUS

Segment C West and N Coast Hwy 101 Drainage Improvements, between Jupiter Street and La Costa Avenue, began construction in March 2024 with anticipated completion expected in Summer 2026.

Excavation and installation of new 60 and 66-inch storm drainpipe began at Jupiter Street and continues northward to La Costa Avenue, with current work happening from Moorgate Road to La Costa Avenue.  This work involves excavation of 25 to 35 feet in depth and includes shoring along the entire trench length to support the deep excavation.   Installation of surface storm drains will occur throughout the project length. 

To date, the Leucadia Streetscape Segment C and the NCH 101 Drainage Project has installed 3,974 linear feet of 60-inch, 108 linear feet of 66-inch, 430 linear feet of 36-inch storm drain pipe, 11 cleanout boxes, 568 feet of 24-inch storm drain and a portion of the west side storm drain inlets.    

The current work continues on the drainage infrastructure, including the large storm drain (60 and 66-inch) placement along North Coast Highway 101 near La Costa Avenue.  A portion of the east side of the roadway will be paved to allow for northbound traffic to continue on the east side of North Coast Highway 101 from Grandview Street to La Costa Avenue. The contractor will continue working on the west side for the smaller storm drains and drainage inlets, median curbs and new water main.  

Pipe installation and related work, such as new water main, storm drain inlets and connector pipes, paving, median curbs, and roundabout construction will continue on the west and east side through Spring 2026. When the underground facilities are in place the surface improvements, sidewalks, curbs, gutters, inlets, and driveways, can begin construction. 

Expect traffic control with intermittent lane shift, along with construction related activities and impacts including noise, dust, lighting, and large construction vehicles.  Access to driveways and businesses will be maintained.  Please support our local Leucadia businesses during construction.

View our Frequently Asked Questions (FAQs) for Segment C West to learn more about the project.

Streetscape Segment C West FAQ's - General
Streetscape Segment C West FAQ's - Businesses
Streetscape Segment C West FAQ's - Trees

  • Segment C - (Jupiter St. to La Costa Ave.) Bicycle and Pedestrian Enhancements, Pavement Improvements, Wider Sidewalks, Designated Bike Lanes, New Roundabouts at Jupiter St. and Moorgate Rd., New Streetlights, Crosswalks and Ped Signal at Avocado St., New Benches, Bike Racks and Hundreds of New Trees.
    Segment C West (Jupiter to La Costa)
    Project Renderings
    Project Timelines
    Click here to view on City Projects Dashboard
  • North 101 Drainage Segment C - (Jupiter St. to La Costa Ave.)                 
    New Drainage Infrastructure to Reduce Flooding and Provide Stormwater Treatment
    being constructed in conjunction with the Leucadia Streetscape Segment C West Project between Jupiter St. and La Costa Ave.   Click here to view the N. 101 Drainage Project Page
    Click here to view on City Projects Dashboard.

    On June 12, 2024 City Council approved additional funding to complete the 60-inch drainage work for the project between Jupiter St. and La Costa Ave.  The additional funding and project scope will extend the construction timeline, with a new completion target date of summer 2026.

Segment C Business Maps

Updated on 06/14/2024 11:39 AM

Please support our local businesses during construction.